Wednesday, March 7, 2012

'SMART Wireless Limited' does it again - Wins bid for Ujjain Distribution Franchisee

After winning Madhya Pradesh's Gwalior Power Distribution Franchisee bid, 'SMART Wireless Limited' has now won the bid for Ujjain city, making it two in a row winner in Madhya Pradesh DF landscape (see our earlier blog 'Gwalior Distribution Franchisee Bid Results - 'SMART Wireless Limited (Essel Group)' emerged as a Winner' for Gwalior bid analytics). The company's winning quote of Levelized Input Rate (LIP) was Rs. 3.781/unit, letting it again overtake other companies in the financial bid. Overall, there were 10 companies, who participated in Ujjain DF bids, out of which 9 were Technically qualified (see list of all technically qualified bidders for Ujjain Distribution Franchisee).

Some brief observations from the price bid are:
  • Minimum LIP was Rs. 2.390/unit among all quoted LIPs.
  • Margin rate between winning and 2nd price bid was Rs. 0.223, approximately 6% lower than the winning bid. The 2nd ranker in the bid is GTL, an existing DF operator at Aurangabad. Note that GTL won Auranganbad DF bid at higher bid LIP of Rs. 3.74/unit.
  • 3rd and 4th bids were respectively 12% and 18% lower than winning bids.
  • 4 out of 9 companies has given the price bid in the range of 2.95 - 3.35 Rs./unit. Two bidded higher  and 3 bidded lower than this range.
  • The bid is aggressive as other established power players are lower by around 20%-25% than winning bid.
About Smart Wireless Ltd. 
The Smart Wireless Ltd. company is into generate new technologies in the messaging space and facilitate technology and process driven companies using cost effective data transfer solutions such as SMS. The Wire segment of the Essel group is currently one of the largest cable distribution system in India, with presence in 54 cities. It will be interesting to see their existing B2C reach also to the power distribution business. Overall the Essel group has wide portfolio in Infrastructure (roads, SEZ, power plants etc.), Media (ZEE, DNA being their leading brands), Technology, Education, and other diversified businesses.

Upcoming Results
Sagar city results are likely to be announced in next week on 12th March. With 'SMART Wireless' as the winner of 2 cities already, it is to be seen if they would do a hat-trick. It is also a question for MP policy makers if they would allow one company to do all the 3 DFs at such aggressive rates and risk non-performance.

Posted by: Kunjan Bagdia @ pManifold

In continuous effort to scale Power Distribution Franchisee business model, pManifold has launched a Market Research Report on Input based Power Distribution Franchisee in India. The report will provide detailed market, operational and financial insights into running a Power Distribution Franchisee. It will also include detailed previous bid analytics, including most recent from MP, future DF opportunities and trends. For more details, please see Table of Contents. You can place your order with us at kunjan.bagdia@pmanifold.com.

Tuesday, March 6, 2012

Gwalior Distribution Franchisee Bid Results - 'SMART Wireless Limited (Essel Group)' emerged as a Winner

'SMART Wireless Limited', an Essel group company emerged as the winner for Madhya Pradesh's Gwalior Power Distribution Franchisee. The company quoted a Levelized Input Price (LIP) of Rs. 4.14/kWh, which enabled them to win and surpass existing DF operators like SPANCO and Torrent Power.

This rate quoted for Gwalior city is highest compared with all previous DF bids.









All 9 companies who participated in Gwalior bid were Technical Qualified (see our earlier blog Total 12 companies participated in Madhya Pradesh's DF bids for list of all received bids and participating companies for MP bids)

Some key observations from the price bid are:
  • Of all quoted LIPs, minimum was Rs. 2.52/unit, coming from an existing DF operator.
  • Average LIP of all quoted bids was Rs. 3.23/unit.
  • Existing DF operators ranked 5th and last in the financial bid. They also quoted lower for Gwalior than their existing won areas.
  • Margin between winning and 2nd price bid was Rs. 0.27/unit, a 7% lower than winning bid.
  • 3rd and 4th bids were respectively 18% and 20% lower than winning bids.

Friday, February 17, 2012

Total 12 companies participated in Madhya Pradesh's DF bids

Madhya Pradesh's Distribution Franchisee bidding at last saw a progress in bidding phase with last 3-4 revisions and deferment. The bidding was closed on 16th February 2012 and total saw 12 companies. The final winners are likely to be announced by 27th or end of Feb.
List of Received Bids from private players for MP Distribution Franchisees

Friday, February 10, 2012

Ujjain DF Webinar: Rs. 70 cr. Capex, given AT&C loss reduction trajectory and Rs. 3.5 Levelised Input price can bring 8.79% Equity IRR

Webinar Brief Introduction
The revised MP Distribution Franchisee (DF) RFP for Ujjain has brought down on average coverage area by 98%, number of consumers and electricity sales by 70% and number of DTCs by 90%, with move from district level to city level. There is now mandated capex of Rs. 70 cr. for Ujjain and target ATC reductions to 15% in 2 years from current 40.82%
The webinar cum workshop will focus on 3 important ‘perspectives’ that plays important role in overall investment analysis of DF business. pManifold ground study results with GIS visualizations from Gwalior city will be shared.
  1. RFP analysis: How have been the load growth trends across different categories of consumers?
    • HT & Commercial growth has picked up well with higher sales growth rate compared to Gwalior.
    • Growth is consistent with indication of lower theft as compared to Gwalior.
  2. Socio Economic analysis: Which socio-economic indicators trend could give insight into future load growth of the region?
    • Ujjain has higher DDP growth rate and workforce participation as compared to Gwalior.
    • Also highest literacy rate, and net sown area in MP.
    • Higher urban slum rate, but lowest ST population in MP.
  3. Utility performance analysis: What key issues related to Power reliability, Metering/Billing/Payment, Customer services, and other service attributes faced by end-customers? Could this be a Lead indicator for required Capex and Opex in the region?
    • What are the major Capex component drivers? What utility performance they target to improve?
    • EUCOPS Study Framework - Further breakdown of CSFs into 27 attributes. They in turn drives to create a ‘functional role’ & ‘performance’ based DF organization
    • Category-wise & geographical localization of factor issues - Outages, Breakdown restoration & Maintenance are key issues affecting all customer categories including revenued ones.
  4. Bid Investment Analysis: What are key parameters and their sensitivity to bidding?
    • Key Results
      • Equity IRR = 8.79%
      • Equity payback = 9 years
      • Avg. DSCR = 1.02
    • Key Assumptions
      • Capex - Capex Rs. 70 cr., 100% refund of depreciated terminal value
      • Opex - 60 paisa per unit employee cost (80% of O&M costs)
      • Input Price - Bid price curve with LIP of Rs. 3.52 (previous slide top green curve)
      • Loss Reduction - Technical Loss reduction rate of 16% per year (cap 6%), Non-Technical Loss reduction rate of 20% per year (cap 4%)
      • Growth - Avg. Tariff growth rate of 3%, Avg. Load growth rate of 7%
      • Investments - Equity 30%, Term Loan Interest rate 13%
      • Taxes - Tax rate 33.22%, MAT 19.93%
Live Discussion and Q&A Q&A
Their will be 45 mins of presentation followed by 15 mins of LIVE Discussion and Q&A. Please consider taking our online survey (if you already have NOT) and share your broad views on MP Distribution Francisee bids to better facilitate this discussion.

Speaker Profile
Rahul Bagdia is Co-founder and Director of pManifold Business Solutions. pManifold is an Information and Advisory services company and has positioned its 'Energy' services to support scale-up of the emerging Distribution Franchisee business model in India. Our services includes:

1. Research
2. Stakeholder Engagement
3. Consulting

Friday, January 13, 2012

Webinar: Market & Customer Intelligence on Gwalior for Distribution Franchisee Bidders


Webinar Brief Introduction

The revised MP Distribution Franchisee (DF) RFPs for Gwalior, Ujjain and Sagar has brought down on average coverage area by 100%, number of consumers and electricity sales by 60% and number of DTCs by 77%, with move from district level to city level. There is now mandated capex of Rs. 170 cr for Gwalior, Rs. 70 cr. for Ujjain and Rs. 30 cr. for Sagar and target ATC reductions to 15% in 2 years.
With 30+ companies in the race, already 3 RFP revisions with wider stakeholder engagement, and removal of stringent cash accrual qualification criterion, the bids will likely be more competitive and also volatile. It has become more important now to integrate various perspectives and data sets of information to validate assumptions and prepare informed bidding numbers.

Content Summary
The webinar cum workshop will focus on 3 important ‘perspectives’ that plays important role in overall investment analysis of DF business. pManifold ground study results with GIS visualizations from Gwalior city will be shared.
  1. RFP analysis: How have been the load growth trends across different categories of consumers?
  2. Socio Economic analysis: Which socio-economic indicators trend could give insight into future load growth of the region?
  3. Utility performance analysis: What key issues related to Power reliability, Metering/Billing/Payment, Customer services, and other service attributes faced by end-customers? Could this be a Lead indicator for required Capex and Opex in the region?

Monday, December 5, 2011

Ongoing survey results preview on MP Distribution Franchisee bidding

A lot anxiety is getting build amongst the bidders and general observers of Madhya Pradhesh Distribution Franchisee bidding. With expected fourth revision in the RFP, there is a silence from MP Govt. side on the topic and next steps including tentative dates. Industry internal resources have pointed that the issue is on hold for cabinet approval. While on one side there is eagerness in existing MP Govt. to see all 9 districts see bidding before next election in 2013. However on other side, there is a fear to enter newly into this very emerging DF business model, when not much of performance (both pros and cons) clearly established from existing operating DFs. Their main concern being "How to protect utility's interest in this long tenure contract with private DF operators?". See our earlier blog Pre-Bid conference take-away from Madhya Pradesh Distribution Franchisee bids.

Keeping this in view, pManifold team floated an online survey of top management of prospective bidder companies (some 30+) for ongoing 3 regions (Gwalior, Ujjain and Sagar) DF bidding. This is an independent survey conducted to increase the understanding of Bidder's issues for MP Distribution Franchisee Bidding and taking it rightly with the policy makers. The responses so far collected are from established companies in the power sector and who have taken this pre-bidding phase very diligently. While not all prospective bidders have responded so far, the results are looking interesting and it is requested that those remaining also take upon this survey soon to let your voice resonate and influence design of RFP revisions. (see survey link. Please note that no personal identification is requested)

Some key questions that this survey intends to find opinion of bidders keeping in mind the ongoing MP bids revisions:

  1. Qualification criterion improvements
  2. Top viability concerns
  3. Anomalies in existing RFP and suggestive key changes
  4. Improvement suggestions to baseline data
  5. Overall satisfaction with MP bidding and stakeholder engagement process
The so far collected response has following highlights:
  • 50% entering first time into the DF bidding
  • 67% of participants qualifies both technically and financially
  • Only 33% are sure for bidding, while rest are still deciding
  • Most interested in Gwalior, followed by Ujjain and then Sagar
  • Almost all satisfied with financial qualification criterion
  • 33% dissatisfied with Technical qualification criterion
  • 33% dissatisfied with the overall bidding process
Some key concerns raised by survey participants:
  • Most finds high mandated capex, strict reduction target and unreliable baseline as serious viability concern. Most understand importance of improved customer services and has seeked more clarity on customer satisfaction performance and evaluation.
  • Major pre-bid support request from bidders is to have certified joint audit of baseline (specially ABR) and guaranteed power supply and non-performing clauses for utility made clear. 
  • Many of them find R-APDRP linkage with DF performance and evaluation not fit, given R-APDRP assets have not been kept well
  • There are requests to further improve transparency in the bidding process and keep all participating pre-bidders well informed on steps, delays, and broad reasons etc. in bid process handling. 

We hope that these results further aid planning and improved design of DF process, possibly the coming RFP revision for MP bids. With this broad objective to support scale-up of DF model, we request DF bidders community to participate actively in this survey and share their non-confidential learnings. (Please click here to take online survey)

Post by Rahul Bagdia @ pManifold

pManifold's services in Distribution Franchisee space: 

Saturday, October 22, 2011

Cheat sheet for Distribution Franchisee

This is a consolidation of our previous blogs, focussed more to help the current bidders for Madhya Pradesh DF bids.

Bidders Perspective
·         Input price: Bid analytics for MP Distribution Franchisee

Utility and Regulators perspective

Local business intelligence on utilities performance - take informed bidding on MP Distribution Franchised towns


The revised MP Distribution Franchisee RFPs has brought down on average coverage area by 100%, number of consumers and electricity sales by 60% and number of DTCs by 77%. Also with mandated capex of Rs. 170 cr for Gwalior, Rs. 70 cr. for Ujjain and Rs. 30 cr. for Sagar and target ATC reductions to 15% in 2 years, the bids will become more competitive and likely also volatile. It has become more important now to integrate various perspectives and data sets of information to validate assumptions and prepare informed bidding numbers. 

pManifold is an Information and Advisory company and is working broadly with relevant stakeholders to help scale-up of the emerging Distribution Franchisee model in India. In this role, we conducted a first type of study to measure Customer Opinions, Preferences and Satisfaction for Electric Utilities of Ujjain, Sagar and Gwalior, which brings a fair customer perspective that could be integrated with technical perspective to arrive at tighter estimates of Capex and Opex. We have compiled a Consolidated report on the 3 towns (priced at Rs. 25K), which could provide winning edge in the MP bids. 

Also available are comprehensive regional packages (priced at Rs. 25K) each consisting of 4 separate reports with GIS visualization and together they could help find answers to the following viability questions:
  1. Customer Satisfaction – Top Results (30+ slides) includes top level findings with attribute and factor level comparisons and recommendations
    • What are the key customer segmentation trends in terms of geographical localization, avg. monthly consumption, economic loss due to power outages, types of meters, backup equipments, education/profession, access to internet, electricity bill payment preferences, opinion on DF privatization etc? (across 4 consumer categories of Residential, Industrial, Commercial & Agri)
    • What are the key issues on Power reliability, Metering/Billing, Customer services, utility communications, utility IT and records handling, Tariff and utility Management as perceived by customers across 28+ attributes? (across for 4 consumer categories and also overall)
    • What areas required capital expenditures to improve overall utility's performance? How to prioritize capital expenditure for highest return on customer satisfaction, which is found to be correlated with ROI?

Thursday, October 20, 2011

Customer segmentation and analytics of revised MP Distribution Franchisee bids

Our earlier blog Urban & Rural customer segmentation in revised Distribution Franchisee bids at MP compares the category wise distribution of number of consumers across the 3 locations of Gwalior, Sagar & Ujjain. This blog summarizes the comparison of other key parameters - Electricity Sales, Revenue Billed and Collection Efficiencies between new & old RFP regions.

Electricity Sales (in LUs)








Key observations from the above table are:
  • Electricity Sales has decreased most in Sagar (>77%), followed by Ujjain (>72%) and Gwalior (>30%).
  • Electricity Sales to 'Irrigation' customers has decreased more than 90% across all the 3 locations indicating that the majority of Agri customers falls outside city limits.
  • Across 'Industrial' customers for all 3 locations, Sagar city has highest drop in Electricity Sales which is more than 70%.

Wednesday, October 19, 2011

Third Pre-bid Conference take-away from Madhya Pradesh Distribution Franchisee Bids

The third pre-bid conference organized by GoMP on 15th October saw participation of 20+ prospective bidders, almost the same list of companies that participated in second pre-bid event with minor new additions. This includes NDPL, Torrent Power Limited, Tata Power, Reliance Infra, GTL Limited, SPANCO, CESC Ltd, Enzen Global Solutions Pvt. Ltd, Essar Power, GMR Energy, Dainik Bhaskar, Adani Power Ltd, Lanco Infratech Limited, A2Z Powertech, Dalmia Bharat Enterprise, Ramky, BLA Power Pvt. Ltd,  Shyam Indus Power Solutions Pvt Ltd, Era Infrastructure Engg Ltd., Agrawal Power Pvt. Ltd, Eltel Engineers Pvt. Ltd, Lanka Electricity Pvt. Ltd. (LECO), Moser Baer and few others. The list includes many first time entrants in the distribution sector with one international participation from LECO group. (See our earlier blog on second pre-bid conference takeaways)

GoMP has revised the Distribution Franchisee boundaries to city/town level from earlier entire district level and has also removed any minimum benchmark input prices. This potentially makes the bidding more favorable to bidders, but at the same time more competitive. See our earlier shared bid analytics and comparison results of old and new RFPs:
One strong message passed by Energy Secretary Mr. Mohd. Suleman was that there will be no further revisions in RFPs and no further delays in bidding dates. He guaranteed 90+% accuracy of baseline data shared in RFPs and reiterated the need for trust between utility and DF operator to further correct/refine any mutually identified issues. One strong non-negotiable point put forth by utility was high customer satisfaction to be guaranteed by DF with 24 hours power supply and improved customer services.

Friday, October 14, 2011

Urban & Rural customer segmentation in revised Distribution Franchisee bids at MP

Our previous blog Key comparison of revised RFPs for MP Distribution Franchisee compare new and old RFPs for Sagar, Gwalior and Ujjain regions across key DF decision parameters. Here we want to study and compare the customer segmentation closely to better understand the dynamics that played key role for design of new RFPs and separation of urban and rural.

Consumer Segmentation in new and old DF RFPs at MP (Source: pManifold)

Some key observations made from above table are:
  1. Sagar and Ujjain towns had 70%+ less number of consumers as compared to respective districts. The new town level geographic area is on average only 2% of the area of the entire district.
  2. Sagar town has significant drop (greater than 70%) in terms of most valued electricity consumers namely HT, Industrial, Domestic and Others
  3. 99% of irrigation customers falls outside the new revised RFP's town boundaries. This indicate a significant presence of agri customers outside city/town limit. 

Thursday, October 13, 2011

Key comparison of revised RFPs for MP Distribution Franchisee

Madhya Pradesh has revised its Distribution Franchisee (DF) RFPs for the 3rd time, inviting a third pre-bid conference on 15th October at Bhopal. (See earlier blog post Pre-Bid conference take-away from Madhya Pradesh Distribution Franchisee bids). Some major revisions in new RFPs are as follows:
  1. The Distribution Franchisee scope has been revised to city/town level from earlier entire district level. Currently only one most favorable town has been picked in each of three MP zones - Sagar, Gwalior and Ujjain. The other six regions will be followed upon post finalizing DF appointment in first three.
  2. In revised RFPs, there are no benchmarking minimum input rates given. The bidders are now free to select their input rates under following constraints:
    • The input rates for 15 years should have only increasing trend
    • Ratio of specified min. to max. input rates should be atleast 0.7
  3. Customer services are given more weightage with mandated capex investment in meeting specified benchmark KPIs - SAIFI, SAIDI, min. customer services centers, consumer indexing and as laid under SOP by state Electricity Regulatory Commission.
  4. In addition to detailing DF's Events of defaults, the revised RFPs detailed Distribution Licensee event of default of not being able to supply committed input units.
In our earlier blog Distribution Franchisee Attractiveness - Comparison for Madhya Pradesh's 9 districts, we ranked key DF decision parameters for 9 districts to help bidders with their selection criterion. The chart below lay down similar comparison for the 3 towns as released under revised RFPs. We have also indicated the percentage deviation of these key parameters from the earlier RFPs at district level.

DF attractiveness Matrix (Source: pManifold)
Some key changes that comes out clearly with the new revised RFPs are as follows:
  1. Avg. 98% reduction in geographical area
  2. Avg. 61% reduction in overall population, number of electricity consumers and also Electricity sales (lac kWh units)
  3. Avg. 51% reduction in connected load
  4. Avg. 1549% increase in electricity consumer density (clearly reveals urban/rural conflict)
  5. Avg 18% and 22% increase in LT and HT consumption respectively (kWh/consumer/month)
  6. Avg. 5% improvement in collection efficiency
  7. Avg. 77% and 63% reduction in number of DTCs and transformer failure rate respectively
  8. Distribution losses on avg. increases by only 2% while ATC losses on avg. reduce by 1%. If the numbers shared in RFPs are correct, this implies that rural areas contribution to the overall distribution and ATC losses is similar to that of urban areas. 
It is clear that the preferred order for established bidders from DF attractiveness will be Gwalior, followed by Ujjain and then Sagar. However for new entrants, Sagar could be a good choice to innovate a low capex and hence lower risk DF model.

pManifold takes pride in able to influence the revised RFP design and bringing more customer focus in on-going reforms attempted in power utilities. This success is also shared with MP Govt., their transaction advisors and also some bidders. With our continued work in the same, we hope to drive the importance and connection of customer monitoring with business financial performance in private and public utilities and help them develop an increased ROI based power Distribution model.

Independent all 3 towns customer intelligence reports 'EUCOPS - Electric Utility Customer Opinion, Preferences and Satisfaction' are available for purchase with pManifold. Sample report could be viewed online. We hope that the bidder community make use of this local customer intelligence to guide it's technical due-diligence better. (See detailed steps)
For more details contact Rahul Bagdia @ 95610-94490.

Post by Rahul Bagdia @ pManifold

Wednesday, October 5, 2011

Bid analytics for MP Distribution Franchisee

Source: pManifold
The old 9 Madhya Pradesh's districts RFPs provided the minimum benchmark input prices for all 15 years as shown in the right. Comparing Gwalior, Ujjain and Sagar below:

  • Gwalior has highest rates, followed by Sagar and then Ujjain for all 15 years. 
  • The delta between the minimum and maximum rates are also highest for Gwalior (Rs. 1.07), followed by Sagar (Rs. 0.45) and then Ujjain (Rs. 0.27).
  • Minimum delta was Rs. 0.05 for Dewas, maximum was Rs. 1.07 for Gwalior and average was Rs. 0.55

Wednesday, September 14, 2011

Key Comparative findings from Customer Satisfaction Survey of Shajapur, Ujjain & Dewas districts of MP

A comparative view of top level findings is shown here, developed using the location specific reports of Shajapur, Ujjain & Dewas available here along with 6 other districts in Madhya Pradesh (MP).

See our earlier blog:

The analysis shows that in the above 3 districts, a substantial percentage of dissatisfaction in
Customers is coming due to 2 factors, namely 'Communication' & 'Price'.


The overall Satisfaction score on being computed
(on scale of 0-100 with 100 being all respondents 'very satisfied'):

Communication Price
Shajapur 33.68 30.76
Ujjain 27.09 32.77
Dewas 24.50 20.90

The main reasons for higher dissatisfaction across the 3 districts as indicated by the customers are due to following:
  • Less 'Awareness' from Utility regarding the attributes 'Energy Efficiency' & 'Consumer Rights'
  • Less communication for 'Advance notice about disruption'
  • 'Power Tariff & its variations' is High

Friday, September 9, 2011

Comparative findings from Customer Satisfaction Survey of Sagar, Satna & Narsinghpur districts of MP

This is a comparative view of top level findings developed using the location specific reports of Sagar, Satna & Narsinghpur available here along with 6 other districts in Madhya Pradesh (MP).

See our earlier blog:

Power Quality & Reliability (PQ&R) and Customer Service (CS) are the 2 factors which needs immediate improvements in all the three districts.

The overall Satisfaction Score is as follows (on scale of 0-100 with 100 being all respondents 'very satisfied'):
PQ&R CS
Sagar 27.02 21.39
Satna 30.56 27.56
Narsinghpur 29.30 29.31

The primary reasons for high dissatisfaction across the 3 districts as indicated by the customers are due to following:
  • Frequent interruptions in 'Voltage Stability',
  • 'Breakdown Restoration Time' is long,
  • Recurrent 'Unplanned Outages'


Tuesday, September 6, 2011

Leveraging Customer Perspective for a stronger Onsite, Local Due-Diligence in Pre-Bid phase

Consumer centricity has returned or finding its way into most of the businesses in emerging economy like India. Consumer 'needs' and 'willingness to pay' for good quality products and services is driving a whole new era of competition. It first started in luxury industry with high economy class consumers, where there was established 'willingness to pay' for better services and then slowly start penetrating into other sectors and also lower economic classes and raising their 'aspirations'. These phenomenon is creating a whole new market and driving innovations from bottom-to-top. The aviation, telecom (mobile and internet) and various other industries has seen this Consumer cycle. India's Power Distribution sector has begin its journey of enabling 'diversity' and adding more 'choices' to its electricity customers. Like other sectors, the cycle first began with high volume or developed consumers through 'top-down' innovation like 'Open Access' and now we have started hearing of 'bottom-up' innovation like 'Pre-paid metering', 'Net-metering' and 'Distributed Generation based Distributed Franchisee (DGBDF)'.

The to-be leaders in the Power Distribution space will soon have to learn this change that is sweeping the country and include the end-consumers into the designing and co-creation of solutions and soon also accept equally the urban and rural consumer mix to drive bottom-top innovation. The new saga is to forgo or overcome references like BPL, APL, agri (or rural), tariff subsidies and free power, but start innovating scalable ventures to meet the needs and challenge. Grameen Micro Financing model first innovated at Bangladesh is now widely accepted and MFI is a very big and fast growing industry with strong developing linkages to the main streamline capital industry through various derivatives.

Remember this all begins with a 3 letter word - KYC i.e. 'Know Your Customer'. Its an important phase after you are done with Market Analysis through KYM i.e. 'Know Your Markets'. KYC should be a pre-cursor for high confidence KYI i.e. 'Know Your Investments'.

Our recent discussions with prospective bidders for Distribution Franchisee tenders in 9 districts of Madhya Pradesh (MP) was full of encouragement for our recently conducted 'Customer Satisfaction study for Electric Utilities' in those regions.
  • Most companies easily perceived our work's importance to operating  Distribution Franchisee post the bid win for regular (internal & external) benchmarking of Customer Satisfaction to evaluate and better prioritize their system investments and efforts.
  • Almost all experienced companies in running Distribution extended the applicability of our Customer Satisfaction research also to the pre-bidding phase. They found it will add an important perspective to their already on-ground technical due-diligence and help them validate their assumptions on Capex and Opex plans for bidding. 

Tuesday, August 30, 2011

Pre-Bid conference take-away from Madhya Pradesh Distribution Franchisee bids

Madhya Pradesh (MP) Energy Dept. has taken a bold step with decision to private franchise 9 MP district’s Power Distribution simultaneously. This is unique as there is less than 9 total operational Input based Power Distribution Franchisees (DF) pan India at the district level scale while the model is still emerging. The associated officials and transaction advisory have incorporated good learning in current RFPs for the 9 districts from previous awarded Distribution Franchisee RFPs (across India) and emerging Distribution Franchisee implementation scale-up issues. There is appreciable effort from Energy Dept GoMP to engage various stakeholders to raise a strong and standardized Distribution Franchisee model.

A second revision in RFPs was made post first pre-bid conference after consulting with participating prospective bidders (See first pre-bid conference minutes). A second pre-bid conference was organized in Bhopal on 25th August jointly for all 9 districts. The meeting was chaired by Hon. Energy Secretary GoMP, Mr. Mohd. Suleman and was attended by overwhelming 20+ prospective bidding companies. pManifold participated in this pre-bid conference based upon their relevant work in the Distribution Franchisee space and having collected valuable customer satisfaction data on local electric utilities performance in the 9 MP districts.

Some key points of discussion raised by Licensee (the utility) for opinion from participating prospective bidders were:
  1. If and how utility not only avoid financial losses as established in baseline, but also make profits in a truely win-win Distribution Franchisee model in long term?
  2. How could utility protect its and its end-consumer's interests better while in Distribution Franchisee long term contractual arrangement? In specific what could be better contract and company structuring - whether utility should sign contract with SPV (Special Purpose Vehicle) or the Parent company?
  3. If and how 'urban' and 'rural' Power Distribution Franchisees could be clubbed together? In specific with current all 9 MP districts having high rural characteristics, how bidders look upon viability of a combined Distribution Franchisee model at entire district level?
It was encouraging to see the utility's Top Management and participating prospective bidders recognizing 'Customer Satisfaction' as the most important performance objective for Distribution Franchisee. In light of this, there was discussion to add some mandated customer services in the RFP and DFA in addition to current 100% Electronic Metering, Billing and Payment as part of Capex roll-out plan. 

Wednesday, August 17, 2011

Three key comparative findings from Customer Survey Results of Gwalior, Datia & Bhind

This is a comparative view of top level findings developed using the location specific reports of Gwalior, Datia and Bhind available here along with 6 other districts in Madhya Pradesh (MP).   


Regional traits like urban/ rural development differentiation are strikingly clear; Customer satisfaction lowest in Bhind

In the overall scheme of things,
  • Bhind district scored a dismal 26.96
  • Gwalior district scored 52.41 & 
  • Datia district scored 58.22
Specifically in Datia, the increased score can be attributed to the respondents in the Commercial category who indicated satisfaction on most major factors under consideration especially their comfort with the current Pricing available to them and also their satisfaction with the Power Quality and Reliability. 


While, long hours of load shedding (6-10 hours), frequent unplanned outages, poor infrastructure and maintenance and poor customer services in Bhind specifically constitute its low score. 


Satisfaction of customers is also relative and consistent to the level of customer’s expectations in different regions.

When asked if they agree that “A lot needs to be done to improve the current systems and make me fully satisfied” comparatively least respondents agreed in Datia (55%) than Gwalior (58%) followed by Bhind (91%) where most respondents agreed they are expecting a lot to be done before they get satisfied with the utility services.


Regions where customer’s believed more needs to be done to make them satisfied scored low on customer satisfaction.



Mixed reactions towards privatization of power distribution through franchisee model in Gwalior, Datia and Bhind
When asked if ““Service levels will improve if a private company manages electricity distribution”
In Gwalior 51% respondents agreed
In Datia 36% respondents agreed
In Bhind 83% respondents agreed

Over 70% of respondents from Commercial Category in both Datia & Gwalior disagreed that privatization would help improve service levels.

Over 80% of respondents in Bhind, both in Residential and Commercial categories, agreed that Privatization will help improve the current situation.

For individual reports on each region, please get in touch with Rahul Bagdia, +91 956 109 4490, rahul.bagdia@pManifold.com.

Monday, August 15, 2011

Update: Rescheduling of Distribution Franchisee tenders in Madhya Pradesh

A previous blog covered the market status of on-going and upcoming projects in Power Distribution Franchisee in Madhya Pradesh (MP).

As per the latest tender notices, Submission Dates has been revised for all the 9 districts in MP.

Another Pre-Bid Conference is scheduled on 25th Aug 2011 for all the 9 districts. The table below provides the revised dates for all the the 9 districts.



(Click on image to see the enlarged view)

References:


  

Saturday, August 13, 2011

Launched: Electric Utility Madhya Pradesh - Report Series 2011


As you know we have been working since the last couple of weeks on capturing the latest insights from electricity customer across upcoming Power Distribution Franchisee areas in Madhya Pradesh, India specifically the regions of Bhind, Satna, Shajapur, Gwalior, Sagar, Dewas, Datia, Narsinghpur & Ujjain.


This 'first of its kind' report series attempts to raise the local customers voice, to enable the distribution franchisee & utility stakeholders to monitor the local situation, identify key priority actions and plan investments & road maps accordingly.

Key features of the report are:
  • Most recent, independent, “indicative, land based, face-to-face” survey providing the customer’s perspective of local electricity utility performance with satisfaction scores, opinions including Distribution privatization and customer preferences (example: preferred mode of payment, communications etc.) with detailed GIS visualization.
  • Most comprehensively parameterized, customer centric “indicator” of the effectiveness of utility performance on 28 well-chosen attributes that appropriately represent key areas like power quality, reliability, metering, billing, payments, information systems and customer services
  • Comes along with Additional independent primary and secondary research for Local Electricity Utility stakeholders specifically Distribution Franchisee bidders and licensees
Download a Snapshot Report which contains details on the Report series including survey motivation, methodology, sample results, report data, GIS visualizations and info-graphics.
OR view it below,