Thursday, October 25, 2012

Part 2 of 2: Interview at Reuters on future of Power Distribution Franchisee model in India

This is sequel to "Part 1 of 2: Interview at Reuters on future of Power Distribution Franchisee model in India". 

Question
: WHY BIDDING PROCESS TAKES SO LONG AND WHY DOES IT ATTRACT SO FEW BIDDERS? WHAT IS FURTHER NEEDED TO STRENGTHEN DF MODEL?
pManifold: Some suggestions on the same are as follows:

Gaps
Impact
Needed Intervention
Inadequate and mis-represented
Baseline information for bidding
·      Irrational bidding
·      Delayed bid decision, because of revisions, and litigation's
·      Financial and Non performance risk from DF operator
·      DISCOM to invest in right Technical and Commercial due-diligence for forming the RFP baseline and have it audited by an independent agency
·      DISCOM taking responsibility of  wrong baseline
Poor stakeholder engagement during the bid process
·      Poor final bid participation
·      Risk of re-tendering to mitigate poorer competition
·      Non-optimal DF terms and conditions, leading to later contractual conflicts, and non performance
·      Engage State Govt., DISCOM, Regulator, Bidders and Utility employees well into the DF conceptualization
·      Increase transparency of processes and decisions
Constrictive, open       
ended and non-optimal contract design
·      Minimum benchmark bid prices, disallow financing creativity from Bidders
·      Constrictive elements like improper Escrow design, unclear asset ownership etc. creates difficulty for financing
·      Constrictive qualification criterion (like asking for end-to-end distribution experience, not allowing consortium bidding) brings poorer participation and hence poorer bid price discovery
·      No clearer SLAs led to poorer performance monitoring 
·      There is need for clearer Exit options, to make the model attractive for private Developers and PE investors
·      Better design of Escrow mechanism to be favourable for bank financing
·      Strong SLAs commitment from both DISCOM & DF:
o  Discom: Committed power supply and quality
o  DF: Meeting AT&C loss reduction targets; making power purchase payments regularly; meeting customer satisfaction and other SLAs.       

Week Governance of the Bid process & final bid evaluation     
·      Multiple revisions of RFP and DFA
·      Delayed bid closing
·      Poorer bid participation
·      Multiple extensions
·      Litigations
·      Delayed Start
·      Increasing transparency of bid process and evaluation
·      Discom taking responsibility of wrong baseline, and delayed decision making
·      Invest in proper stakeholder         engagement and online bid room/portal                                
Poorer access to finance to Operationalizing DF (both high Working Capital requirements and Capex for first 3 years)
·      Delayed start of the project
·      Hiccups and non-performance in first year, which further exaggerates opposition against DF model
·      Making Bankers and broader Finance community understand DF model better, and distinguish it from debt burden utility
·      Forming DF initial viability funding from nodal agencies like PFC, REC etc.
·      Allowing right consortium partnership with competent partners on Technical, Operational, Management and Financial side.
·      Improving constrictive clauses in contract design, to allow DF to procure easy bank financing
Weak SLAs to     Monitor Performance of DF     
·      Increase opposition to DF model, without any quantified performance assessment
·      Have clearer milestone, with right incentive/penalty mechanism to encourage performance
·      Have independent customer satisfaction assessment, to establish true metrics for end quality impact from DF model
·      Have transparent reporting mandatory for DF to Regulators
Weak Regulatory      purview of DF model
·       Weak Performance monitoring            
·      DF to stand alone report performance from baseline to ERC (together with Utility)
·      If DF is able to meet its target AT&C reductions, then its customers should benefit with tangible returns (like              either reduced tariff rates as compared to state level Tariff, or reduced load shedding, etc.)  
Weak integration     between different reform schemes (like R-APDRP,    
National Electricity Fund, DF, RGGVY,etc)
·      Poorer end performance i.e. not much AT&C loss reduction, poorer PQR, and dissatisfied customers                           
·      Ensure well integration of R-APDRP and DF projects, to guarantee DF operators with full amount and timely completion of R-APDRP project
·      Ensure interest subsidy from National Electricity Fund
·      No Service tax liability on DF model
·      Allow Electricity duty collected from customers to be used towards Working capital loan



Question: WHAT’S THE FUTURE OF INPUT-BASED FRANCHISE MODEL IN INDIA?
pManifold:
  • At pManifold, we tend to believe the future of DF model is very strong, and infact only way to really bring more accountability and decentralization to the power distribution business, which otherwise is the weakling in the overall power value chain. The model of course needs to be strengthened, and some key improvements are shared above.
  • All our decentralized & alternative Generation efforts will not scale, until we have a strong distribution mechanism, and DF has that potential. So we are looking forward to right regulatory changes to bring integration of these models for better ‘Open Market’ with stronger Private participation:
    • Distributed Generation
    • Distribution Franchisee
    • Open Access (with net metering provisions for smaller generators as well)
    • Energy Efficiency and DSM
  • A much bigger rural market for DF is still awaiting innovation. (See our blog Rural Franchisees - Could they become pilot ground to raise next level of Distribution services?
  • India’s Telecom sector has proved how open market mechanism with supporting Regulations and increased private participation has helped increase mobile penetration, reduce tariff rates, and increase customer services. Same is now looked upon in the Power sector, and I feel we are closer now.
  • The future is bright, if all stakeholders can really work together. CUSTOMERS are the most important link for success of a DF model. The operator that can give more choices to Customers, and meet their PERCEPTION, while manage its Business PERFORMANCE, will succeed. That is the whole reason, that pManifold has developed EUCOPS (Electric Utility Customer Opinion Preferences and Satisfaction) to capture customers voice, and help DF and utility operators track their end performance, as seen by customers. We are glad that more and more DF operators have started using our customer engagement services, and we have worked at Nagpur, Gwalior, Ujjain, Sagar and Dhenkanal, interacting with 7000+ customers from urban and rural. 
  • Customers cooperation is must for DF success, and there is not much in current models to incentivize customer support, as Tariff rates are set at State level. So DF customers will continue to pay higher for inefficiencies in other circles. A tangible and good incentive model within regulatory purview to DF customers (like reduced tariff rates, higher power availability, no reliability charges, reduced Electricity duty or Demand charges etc.), can further expedite DF operationalization. This will also create pressure on local civic bodies to compete and support DF models in their regions, and faster penetration of DF model including in rural areas as envisioned by Planning Commission.

Question: WHAT ARE OTHER FRANCHISE MODELS IN INDIA AND HOW SUCCESSFUL THEY ARE?
pManifold:

Posted by: Kunjan Bagdia @ pManifold

Part 1 of 2: Interview at Reuters on future of Power Distribution Franchisee model in India

Rahul Bagdia is Co-Founder and Director
of pManifold. The co. specialize in Utilities and
Emerging Markets Research  and Advisory,
and is focusing upon operationalisation and improvement in
Service Delivery of Power Distribution models.
Reuters recently published an article on Power Distribution Franchisee model in India. The background was taken from bench-marking observations of DF model at Agra and Bhiwandi. See Punchups, kidnappings mar efforts to privatize power for detailed article. pManifold's help was used to understand broader DF market dynamics, through its report 'Input based Power Distribution Franchisee Market in India 2012Q1', and also few rounds of telephonic discussions and email exchanges. Since views from pManifold were not fully captured in this article, we thought of sharing the excerpt here for broader industry benefit. These are personal views of pManifold Director, Mr. Rahul Bagdia. It is divided into two blogs. 

Question: 
DESPITE BHIWANDI’S SUCCESS, WHY MOST STATES HAVEN’T ADOPTED THE FRANCHISE MODEL?  
pManifold: 
  • Input Based DF model is still an emerging model, with last 2 years (2010 - 2012) seeing 4 realizations - 3 in Maharashtra (Nagpur, Aurangabad and Jalgaon), and one in UP (Agra). The year 2012-13 will see another 3 realizations in MP (Gwalior, Ujjain and Sagar), another 2 in Jharkhand (Ranchi and Jamshedpur) and 13+ regions in Orissa under different variant of DF model.
  • There are other ongoing DF efforts, which have been suspended and/or still awaiting final decisions (Mumbra-Shil-Kalwa in Maharashtra; Dhanbad in Jharkhand; Patna and 2 others in Bihar and 3 SAIL projects). All stakeholders are still in wait and watch mode, to see next demonstrated success in DF model. Its matter of another 1-2 years to see model’s fast emergence, with proven performance. 
  • Torrent operated Bhiwandi and Agra models, with different success rates itself demonstrates that DF model has much more operational dynamics and is very regional and customer oriented model, and cannot be solved just by Technical competence in distribution. There are many more factors that influence success of the model, and all Stakeholders Engagement is must.
  • We also see missing strategic planning with most of the operating and new starting DFs. Everyone is trying to re-invent the wheel, and starting from scratch. What is needed, is companies to collaborate with right domain partners from day one, and this is more important with newer players entering into this sector. In specific, at pManifold we see following 3 separate functional/domain roles, that a new starting DF operator should empower with right partners:
    • Network and Line Management (reduce Technical losses)
    • Metering, Billing, Collection and integrated Energy Auditing (reduce Commercial losses)
    • IT, Data Analytics and Customer Satisfaction Monitoring Cell (increase Customer co-operation & overall performance monitoring) 
  • In my various interactions, I have found that Discoms seniors and top management still does not have all clarity on the DF model, and there is an urgent need of strong education on DF model. (pManifold with this aim is planning a workshop and present an integrated model of Utility and DF financials, to help utilities better understand various trade-offs)

Question: WHY THE FRANCHISE MODEL HASN'T REALLY ATTRACTED BIGGER OR FOREIGN PLAYERS?
pManifold:
  • Inadequate and mis-represented Baseline data, and week Governance of the overall Bidding process has led to poor participation and lower confidence in established Developers and Investors.
  • Big players have been strongly advocating full privatization model instead of Franchise in order to have more control levers including Tariff setting to turn around the power distribution scenario. Despite this, they have shown interest in the Distribution Franchise model, and that is the reason they have actively participated in almost every pre-bids, but then, have either refrained from final bidding or have given very low price bids. Their risk averseness to DF’s evolving Contractual & Regulatory terms and conditions in this ‘Emergent’ phase is keeping them on back seat. They are closely watching the DF model to get into the ‘Growth’ and ‘Maturity’ phases, and claim their share. Until then, DF model is really for new players to bring innovation and market inflection with right domain partnerships, and not reinventing wheel.
  • While they are right on few counts, but looking at the diversity of the country (both rural and urban), and being realistic on the continuing political influence on power in the emerging energy/climate economy, we tend to believe that DF model has better chance to scale-up than full privatization model. 
  • There is good foreign companies' interest in Water privatization than Power distribution. Some key distinct features of Water compared to Power are:
    • Urban city Water project has larger budget
    • There is stronger component of Technology in Water Treatment, which Indian players are still not fully equipped
    • Also water is more decentralized than power, with local Municipality (ULB) regulating tariff
    • In Water RFPs, there is likely more weight on Technology, which is forcing Indian companies to actively look for right Foreign partner, which is not the case in Power
  • There is strong advocacy of full privatization by Biggies in this space. Unfortunately, there does not exist an association of DF companies. I see a growing need of an association, to support and advocate DF model, and help it evolve and scale-up. This role is currently played by pManifold, but we need to become more official with this, with support from all small and big DF players in the country. 

Sunday, October 14, 2012

Case Study: Willingness To Pay for Water

There has been an uncertainty around the success of the PPP models in the Indian Utility Market. While some of the fears are well placed, I think that one of the best ways to counter the apprehensions over the revenue projections of the operators, is the Willingness-to-Pay (WTP) analysis of the consumers in question.

The WTP analysis provides a localized and a  stratified consumer response across the socio-economic categories, if well planned and executed. The figure below shows a typical boxplot drawn for a consumer analysis done for one of our clients.
Box-Plot for a typical WTP Study

The client - a private PPP Water Utility operator - had taken over the water supply project of a town with approx 2 lacs consumers. The operator had approached a leading institution for financing the over INR 1000 Cr.

The institutional investor had his apprehensions about the revenue projections and had approached us to do the top-line validation through a WTP Survey and Analysis.

The existing water supply condition of the city was very poor and residents were facing utmost difficulties in meeting their requirements through the ULB supplied water.

We designed the WTP Study using the Contingent Valuation Methodology (CVM) and developed the  framework to execute the study. Key findings, which can be generally seen across other Water consumers, are shown in the adjoining figure.
Key Findings of the WTP Study

The findings helped the operator impress the necessity of the improved quality of water supply and prove that the people, if provided with better services, are willing to bear the cost for the service improvement as well.

The WTP Study did manage to help the operator get to the financial closure.

As we discussed the findings and success story of the WTP Study, we are now engaging with clients not just from the Utility Operators, but even from other service sector enterprises who want to validate their top-line projections before launching new or improved services.

Thursday, September 20, 2012

Challenges in and Levers for success of the 24x7 water supply projects in India


As one wonders what has been holding back the operationalization of the 24x7 water supply projects in India, we thought of penning down our observations around it.

Even before kicking-off the operations, one observes that the long gestation period (5+ years) to engage and realize even first pilot is a show-stopper. This is primarily because of:
    • lack of standardization of the model, and various agency issues at Central, State & ULB level
    • delays in contract sign-off & getting consensus on SLAs and new Tariff agreement
    • Delayed financial closures - constricted investments flow from investors, because of perceived high risk of regulated (& politicised) utility
Levers for Successful Implementation of 24x7 Projects

As the operators take-over and start the operations, the first challenge hitting them in the face is the inaccurate baselines. Revisions in tariff, SLAs, employee deputation follow. The lack of education of customers, employees and local politicians on the PPP models affect all the other stakeholders. 

The nascency of the industry has created an acute shortage of skilled middle management resources that are ready to engage on-ground in Tier-2/3 towns. Further to this, the lack of investment from operators in Strategy, Structure, Systems and Processes, and doing it right from long term perspective creates a totally different shade of problems.

The technological levers of GIS modelling based on low confidence data collection, and fast obsoletion, no useful optimization and design possible. Only static view is captured on GIS and no real  updates happen in the system. Even though water metering (bulk and end-customers) and regular auditing is being stressed upon & invested in, no useful actions are enforced based on analytics. (Power sector has long been metering and doing energy audits, but losses have only increased, because of missing actions. Water is just starting to walk on same trail, and will likely see similar results.)

Finally, there seems to be a total lack of SLAs performance monitoring and enforcement institution. This gives rise to ever-moving targets, and cross blaming.

Overall, currently Management change, and Technology are being stressed upon for the success of 24x7 water supply projects. We believe that there is a need for two additional levers - Performance Monitoring and Customer Engagement, to bring effective Change Management. We strongly believe, that its operationalisation of these models that has to be improved, and rest will follow. 

Wednesday, September 5, 2012

Delayed Bids opening: Perceived risks from 'few & new' players

Both Mumbra-Shil-Kalwa and Jharkhand Distribution Franchisee (DF) bids are pending for bid opening for more than a month. SAIL has only recently open the Bhilai bid, while other 3 areas are still pending. There seems no check on the utilities to monitor governance on the bid process, and be responsible to its bidders. One likely inferred reason for this delayed response from DISCOM is its perceived risk of non-performance from following:

  • Few number of bids received 
    • Mumbra: 3 out of 11 RFP purchasing companies
    • Jharkhand: 2 out of 6 only qualified companies
  • Most new entrants, with no prior experience in the Distribution business
    • Mumbra: Konark, Saicare InfoSystem (SIS) and Supreme Infra
    • Jharkhand: JV of Essel & Enzen and CESC

There are increasing risks of Mumbra bid getting scrapped, looking at continuing delays of bid opening date, and previous legacy of bid scrapping with 5 bidders that time. Similar is the case with Jharkhand, with 2 bids received each for Ranchi and Jamshedpur, and only one for Dhanbad. It is understood, that the overall market confidence on DF model is low at the moment, mainly because of reported contractual non-performance at Nagpur and Aurangabad DFs. Also there has been no recent success story on DF model post Torrent at Bhiwandi. These apprehensions of high risk of another failure with a new player is what is likely leading the utility to consider bid scrapping.

While above utility apprehensions might have some grounds, the opposite of it i.e. 'an established & experienced player will do good' has also examples, that were found untrue. For example:

  • same Torrent, is struggling to stabilise the Agra model
  • Reliance continue to struggle with Orissa, and has itself invited different versions of DF models with limited success
So it is not the limited experience of new players, that is causing current slow down in DF, but its the Model characteristics & its resulting forced dynamics from lack of proper planning, and non-involvement of relevant stakeholders during the design phase. The non-attractiveness of the DF model in its existing form to bankers is not only SPANCO's and GTL's problem, but it's a high risk to all other bidders as well.